Back to projects

Radio communication system

Longueuil, Quebec

completePublic TransitPTIF
Federal contribution
$462,512
Federal share50%

of $925.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
201820192020202120222023
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Feb 28, 2018(actual)
Construction end
Feb 17, 2023(actual)

Also in Longueuil