Upgrade of the Réseau de transport de Longueuil (RTL) control centre camera system and/or access at the cameras of Longueuil station
Federal contribution
$19,137
Federal share50%
of $38.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
201820192020
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de Longueuil (RTL)
- Construction start
- Nov 28, 2017(actual)
- Construction end
- May 8, 2020(actual)
Also in Longueuil