Improvement of installations at the Geoffrion/PWC stop

Longueuil, Quebec

completePublic TransitPTIF
Federal contribution
$124,833
Federal share50%

of $249.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 13, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 1, 2018(actual)
Construction end
Jul 17, 2020(actual)

Also in Longueuil