Transit system improvement plan for the 2020 horizon
Federal contribution
$120,940
Federal share50%
of $241.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
2018201920202021
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de Longueuil (RTL)
- Construction start
- Aug 6, 2018(actual)
- Construction end
- Apr 30, 2021(actual)
Also in Longueuil
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51131 in the federal list. How to read these figures.