Back to projects

Installation of passenger counting systems on buses (SAEIV)

Longueuil, Quebec

completePublic TransitPTIF
Federal contribution
$20,532
Federal share50%

of $41.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
2017
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jan 1, 2017(actual)
Construction end
Sep 12, 2017(actual)

Also in Longueuil

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51143 in the federal list. How to read these figures.