IT improvements Decision-support tools for operations
Federal contribution
$14,049
Federal share50%
of $28.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
2018
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de Longueuil (RTL)
- Construction start
- Jul 10, 2017(actual)
- Construction end
- Apr 25, 2018(actual)