Back to projects

Improved scheduling and assignment planning process

Longueuil, Quebec

completePublic TransitPTIF
Federal contribution
$99,584
Federal share50%

of $199.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 13, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Apr 1, 2017(actual)
Construction end
Sep 18, 2020(actual)

Also in Longueuil

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51153 in the federal list. How to read these figures.