Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Wahta Mohawks
Construction start
Feb 16, 2018(actual)
Construction end
Sep 26, 2018(actual)

Against the original forecast

  • Construction start11 months lateforecast Apr 1, 2017
  • Construction end18 months earlyforecast Mar 31, 2020