Water Treatment Plant Rehabilitation & Upgrades
Oneida Nation of the Thames, Ontario
Federal contribution
$68,343
Federal share43%
of $160.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020
Built
Approved 4 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Oneida Nation of the Thames
- Construction start
- May 1, 2018(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start17 months lateforecast Dec 1, 2016
- Construction end5 months lateforecast Oct 31, 2019
Also in Oneida Nation of the Thames
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51183 in the federal list. How to read these figures.