Construction of a service centre at the Lagueux station
Federal contribution
$134,229
Federal share50%
of $268.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 21, 2017
201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Société de transport de Lévis (STL)
- Construction start
- Mar 19, 2019(actual)
- Construction end
- Mar 31, 2020(actual)
Also in Lévis