Extension of Rapibus busway - Labrosse/Lorrain section
Federal contribution
$3.1M
$3,148,704
Federal share50%
of $6.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 29, 2017
20172018201920202021
Built
Approved 14 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Société de transport de l'Outaouais (STO)
- Construction start
- Aug 6, 2018(actual)
- Construction end
- Dec 31, 2020(actual)
Also in Gatineau
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51248 in the federal list. How to read these figures.