Back to projects

Purchase of 6 articulated hybrid buses in 2017

Gatineau, Quebec

completePublic TransitPTIF
Federal contribution
$3.5M
$3,500,000
Federal share50%

of $7.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 29, 2017
2017
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Sep 12, 2016(actual)
Construction end
Oct 11, 2017(actual)

Also in Gatineau