Garage expansion and modernization

Sherbrooke, Quebec

completePublic TransitPTIF
Federal contribution
$3.0M
$2,975,586
Federal share50%

of $6.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 18, 2018
20182019
Built

Approved 9 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 4, 2018(actual)
Construction end
Oct 31, 2019(actual)

Also in Sherbrooke