Back to projects

Improvements at the Carrefour de l’Estrie Shopping Centre (transfer point for the Société de transport de Sherbrooke)

Sherbrooke, Quebec

completePublic TransitPTIF
Federal contribution
$66,158
Federal share50%

of $132.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 24, 2017
201820192020
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jul 8, 2019(actual)
Construction end
Dec 20, 2019(actual)

Also in Sherbrooke