Back to projects

Repairs to reserved bus lane (Université de Sherbrooke)

Sherbrooke, Quebec

completePublic TransitPTIF
Federal contribution
$62,760
Federal share50%

of $125.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 24, 2017
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Aug 1, 2017(actual)
Construction end
Sep 30, 2017(actual)