Alaska Highway Intersection Improvements

Whitehorse, Yukon

completeHighways and RoadsSCF
Federal contribution
$3.2M
$3,218,085
Federal share75%

of $4.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2017
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Government of Yukon
Construction start
Jul 26, 2017(actual)
Construction end
Nov 1, 2017(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 1, 2017
  • Construction end2 months lateforecast Aug 30, 2017