Back to projects

Study on implementing an on-demand transportation service

Sherbrooke, Quebec

completePublic TransitPTIF
Federal contribution
$25,000
Federal share50%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 24, 2017
2018
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Oct 1, 2017(actual)
Construction end
Jul 9, 2018(actual)

Also in Sherbrooke

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51295 in the federal list. How to read these figures.