Study on implementing an on-demand transportation service
Federal contribution
$25,000
Federal share50%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 24, 2017
2018
Built
Approved 2 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Société de transport de Sherbrooke (STS)
- Construction start
- Oct 1, 2017(actual)
- Construction end
- Jul 9, 2018(actual)
Also in Sherbrooke
- South bypass of the Sherbrooke agglomeration by extending Highway 410 - Phase II$35.6M
- Expansion of Cabana Operations Center$30.8M
- Acquisition of 40 electric buses$24.8M
- Multipurpose Centre at Bishop's University - Sherbrooke$13.2M
- Renovation of Sherbrooke, Deauville and Brompton water treatment plants$6.5M