Alaska Highway Restoration – Km 1454 to km 1475

Whitehorse, Yukon

completeHighways and RoadsSCF
Federal contribution
$1.6M
$1,582,513
Federal share75%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2017
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Government of Yukon
Construction start
May 15, 2017(actual)
Construction end
Nov 10, 2017(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jun 1, 2017
  • Construction end6 weeks lateforecast Sep 30, 2017