Alaska Highway Pavement Overlay
Federal contribution
$1.5M
$1,541,250
Federal share75%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2017
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Government of Yukon
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Oct 1, 2017(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2017
Also in Whitehorse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51307 in the federal list. How to read these figures.