Alaska Highway Surface Upgrades

Whitehorse, Yukon

completeHighways and RoadsSCF
Federal contribution
$744,750
Federal share75%

of $993.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2017
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Government of Yukon
Construction start
Jun 25, 2017(actual)
Construction end
Aug 22, 2017(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2017
  • Construction end6 weeks earlyforecast Sep 30, 2017

Also in Whitehorse

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51309 in the federal list. How to read these figures.