Back to projects

Renovation of the 2000 Berri building

Montréal, Quebec

completePublic TransitPTIF
Federal contribution
$9.4M
$9,353,356
Federal share50%

of $18.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2018
20172018
Built

Approved 9 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Sep 1, 2016(actual)
Construction end
Jun 30, 2018(actual)

Also in Montréal