Green Sand Filter(s) Replacement

Mississauga First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$67,221
Federal share24%

of $282.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Mississauga First Nation
Construction start
Oct 9, 2017(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start9 months lateforecast Jan 17, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51353 in the federal list. How to read these figures.