Repairs and Upgrades at Water Treatment Plant
Fort Albany First Nation, Ontario
Federal contribution
$37,705
Federal share50%
of $75.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Fort Albany First Nation
- Construction start
- May 1, 2018(actual)
- Construction end
- Jul 31, 2020(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 1, 2018
- Construction end4 months lateforecast Mar 31, 2020
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51360 in the federal list. How to read these figures.