Back to projects

Permanent Back up power to sewage lift stations

Long Lake First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$53,727
Federal share50%

of $107.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Feb 28, 2017(actual)
Construction end
Mar 18, 2018(actual)