Valve Replacement
Seine River First Nation, Ontario
Federal contribution
$20,000
Federal share50%
of $40.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Seine River First Nation
- Construction start
- May 30, 2019(actual)
- Construction end
- Jan 30, 2020(actual)
Against the original forecast
- Construction start2.2 years lateforecast Apr 1, 2017
- Construction end3 months lateforecast Oct 30, 2019
Also in Seine River First Nation
- Seine River Community Centre Renovations$3.0M
- Seine River Water Treatment Distribution System Rehabilitation$1.5M
- Repairing the Control Panel in Water Treatment Facility that controls all functions related to running solenoids, dosing pumps, and backwash capabilities that were once present$25.0K
- Replacing or adding to the Filter Media inside the filter media tanks that provides filtration of particles present in the inflowing water from the treatment cycle after flocculation.$7.0K
- Lagoon inlet pipe/valve replacement$5.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51372 in the federal list. How to read these figures.