Rehabilitation of Water Treatment Plant, including the computer monitoring system and ozone systems
Federal contribution
$66,076
Federal share50%
of $132.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedOct 10, 2017
ApprovedMar 27, 2018
201820192020202120222023
Built
Approved 6 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Aundeck Omni Kaning First Nation
- Construction start
- Feb 1, 2018(actual)
- Construction end
- Dec 30, 2022(actual)
Against the original forecast
- Construction start10 months lateforecast Apr 1, 2017
- Construction end6 months lateforecast Jun 30, 2022