Back to projects

Rehabilitation of Water Treatment Plant, including the computer monitoring system and ozone systems

Aundeck Omni Kaning, Ontario

completeDrinking WaterCWWF
Federal contribution
$66,076
Federal share50%

of $132.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 10, 2017
ApprovedMar 27, 2018
201820192020202120222023
Built

Approved 6 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Feb 1, 2018(actual)
Construction end
Dec 30, 2022(actual)

Against the original forecast

  • Construction start10 months lateforecast Apr 1, 2017
  • Construction end6 months lateforecast Jun 30, 2022