Chippewas of Kettle and Stony Point Water Treatment Plant and Distribution Capital Plan
Chippewas of Kettle and Stony Point First Nation, Ontario
Federal contribution
$106,500
Federal share50%
of $213.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
20182019202020212022
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Chippewas of Kettle and Stony Point
- Construction start
- Apr 16, 2018(actual)
- Construction end
- Aug 22, 2022(actual)
Against the original forecast
- Construction start13 months lateforecast Mar 30, 2017
- Construction end4 months lateforecast May 1, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51389 in the federal list. How to read these figures.