Detailed Wastewater System Assessment and Identification of Alternatives to Meet Guidelines and Future Community Environmental and Health and Safety Needs
Grassy Narrows First Nation, Ontario
Federal contribution
$84,900
Federal share50%
of $169.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
20182019202020212022
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Grassy Narrows First Nation
- Construction start
- Aug 5, 2019(actual)
- Construction end
- Jun 10, 2022(actual)
Against the original forecast
- Construction start2.3 years lateforecast Apr 1, 2017
- Construction end6 weeks lateforecast Apr 30, 2022
Also in Grassy Narrows First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51396 in the federal list. How to read these figures.