Water Treatment Upgrades and Repairs

Kitchenuhmaykosib Inninuwug First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$45,100
Federal share50%

of $90.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020202120222023
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
May 1, 2019(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction start2.2 years lateforecast Feb 6, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51398 in the federal list. How to read these figures.