Lagoon Replacement
Federal contribution
$2.6M
$2,597,134
Federal share43%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
20182019
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Rural Municipality of Riverdale
- Construction start
- Jul 16, 2018(actual)
- Construction end
- Sep 30, 2019(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51401 in the federal list. How to read these figures.