Water Treatment Plant Communication System Rehab/Upgrade

Ochiichagwe'Babigo'Ining Ojibway Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$56,915
Federal share50%

of $113.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018201920202021
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 16, 2018(actual)
Construction end
Dec 31, 2020(actual)

Against the original forecast

  • Construction start18 months lateforecast Jan 9, 2017
  • Construction end9 months earlyforecast Sep 30, 2021