Update the current Capital Planning Study to provide additional well water supply for the water plant

Dokis First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$55,109
Federal share31%

of $180.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Dokis First Nation
Construction start
Jan 25, 2018(actual)
Construction end
Feb 19, 2020(actual)

Against the original forecast

  • Construction start12 months lateforecast Feb 1, 2017
  • Construction end6 weeks earlyforecast Mar 31, 2020

Also in Dokis First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51414 in the federal list. How to read these figures.