Back to projects

Water servicing for the south and east sides of Georgina Island

Chippewas of Georgina Island, Ontario

completeDrinking WaterCWWF
Federal contribution
$53,304
Federal share45%

of $117.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018201920202021
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Dec 1, 2017(actual)
Construction end
Jun 30, 2021(actual)

Against the original forecast

  • Construction start8 months lateforecast Apr 1, 2017
  • Construction end9 months earlyforecast Mar 31, 2022

Also in Chippewas of Georgina Island

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51415 in the federal list. How to read these figures.