Back to projects

Repairs and upgrades to Sewage Lagoon

Attawapiskat First Nation, Ontario

underwayWastewaterCWWF
Federal contribution
$15,050
Federal share50%

of $30.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018202020222024
BuiltForecast

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Attawapiskat First Nation
Construction start
Aug 1, 2019(actual)
Construction end
Mar 31, 2024(forecast)

Against the original forecast

  • Construction start2.5 years lateforecast Feb 1, 2017

Also in Attawapiskat First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51418 in the federal list. How to read these figures.