Culvert Replacement

Algonquins of Pikwàkanagàn First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$70,436
Federal share50%

of $142.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 9, 2018(actual)
Construction end
Jul 24, 2018(actual)

Against the original forecast

  • Construction start17 months lateforecast Feb 1, 2017
  • Construction end8 months lateforecast Dec 1, 2017

Also in Algonquins of Pikwàkanagàn First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51423 in the federal list. How to read these figures.