Wastewater Lagoon Berm Rehabilitation

Naicatchewenin First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$25,000
Federal share50%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
20182019
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Naicatchewenin First Nation
Construction start
May 1, 2018(actual)
Construction end
Dec 18, 2018(actual)

Against the original forecast

  • Construction start13 months lateforecast Apr 1, 2017
  • Construction end15 months earlyforecast Mar 31, 2020