Upgrades at sewer lagoon
Temagami First Nation, Ontario
Federal contribution
$16,500
Federal share50%
of $33.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Temagami First Nation
- Construction start
- Jun 1, 2019(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start2.3 years lateforecast Feb 15, 2017
- Construction end3 months lateforecast Dec 31, 2019
Also in Temagami First Nation