Community Wide Stormwater Improvement
Wahgoshig First Nation, Ontario
Federal contribution
$55,990
Federal share50%
of $112.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Wahgoshig First Nation
- Construction start
- Oct 9, 2019(actual)
- Construction end
- Jun 15, 2020(actual)
Against the original forecast
- Construction start2.6 years lateforecast Feb 15, 2017
- Construction end12 months lateforecast Jun 30, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51439 in the federal list. How to read these figures.