Back to projects

Community Wide Stormwater Improvement

Wahgoshig First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$55,990
Federal share50%

of $112.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Wahgoshig First Nation
Construction start
Oct 9, 2019(actual)
Construction end
Jun 15, 2020(actual)

Against the original forecast

  • Construction start2.6 years lateforecast Feb 15, 2017
  • Construction end12 months lateforecast Jun 30, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51439 in the federal list. How to read these figures.