Detailed Water Treatment System Assessment and Infrastructure Planning

Chapleau Cree First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$52,574
Federal share50%

of $105.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Chapleau Cree First Nation
Construction start
Sep 1, 2018(actual)
Construction end
Oct 30, 2020(actual)

Against the original forecast

  • Construction start17 months lateforecast Apr 1, 2017
  • Construction end2 months earlyforecast Dec 31, 2020