Membrane Filter Replacement at Plant

Eagle Lake First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$65,635
Federal share50%

of $131.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Eagle Lake First Nation
Construction start
Jun 5, 2017(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast Mar 15, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51442 in the federal list. How to read these figures.