Aroland First Nation Sewage Lagoons Remediation

Aroland First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$32,750
Federal share50%

of $65.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
20182019202020212022
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Aroland First Nation
Construction start
Oct 30, 2017(actual)
Construction end
Aug 9, 2022(actual)

Against the original forecast

  • Construction start6 months lateforecast May 15, 2017
  • Construction end7 weeks earlyforecast Sep 30, 2022