Effluent Quality Monitoring System
North Spirit Lake First Nation, Ontario
Federal contribution
$68,982
Federal share50%
of $138.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- North Spirit Lake First Nation
- Construction start
- Jul 1, 2018(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start15 months lateforecast Apr 15, 2017
- Construction end3 months earlyforecast Mar 31, 2020
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51484 in the federal list. How to read these figures.