Repairs and upgrades to Pumphouse.

Taykwa Tagamou First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$250
Federal share13%

of $2.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Taykwa Tagamou Nation
Construction start
Jan 1, 2019(actual)
Construction end
Aug 31, 2020(actual)

Against the original forecast

  • Construction start23 months lateforecast Feb 1, 2017
  • Construction end2.5 years lateforecast Mar 1, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51485 in the federal list. How to read these figures.