Rebuild primary clarifier drive system
Deer Lake First Nation, Ontario
Federal contribution
$51,278
Federal share49%
of $105.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
2018201920202021
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Deer Lake First Nation
- Construction start
- Jul 1, 2018(actual)
- Construction end
- Aug 30, 2021(actual)
Against the original forecast
- Construction start16 months lateforecast Mar 1, 2017
- Construction end2 months lateforecast Jun 30, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51488 in the federal list. How to read these figures.