Devils Gap Lift Station Backup Generator Purchase

Wauzhushk Onigum First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$25,000
Federal share50%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Sep 30, 2019(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start2.3 years lateforecast Jun 1, 2017