Waterline installation

Serpent River First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$12,798
Federal share41%

of $31.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Serpent River First Nation
Construction start
Jul 3, 2017(actual)
Construction end
Nov 10, 2017(actual)

Against the original forecast

  • Construction start8 months lateforecast Nov 1, 2016
  • Construction end11 months lateforecast Dec 1, 2016