Upgrade of a Community Owned Wastewater System Servicing a 17 home Sub-Division and Public Daycare Located on Stoneridge Circle, Ohsweken, Ontario, N0A 1M0
Six Nations of the Grand River, Ontario
Federal contribution
$25,622
Federal share50%
of $51.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Six Nations of the Grand River
- Construction start
- Jul 1, 2019(actual)
- Construction end
- Mar 30, 2020(actual)
Against the original forecast
- Construction start22 months lateforecast Sep 14, 2017
Also in Six Nations of the Grand River
- Save the Evidence Phase 3: Exterior Restoration and Public Accessibility$7.6M
- Six Nations Campus Green Retrofits$2.8M
- Construction of a Roundabout at the Intersection of Highway 54 and Chiefswood Road$938.3K
- Six Nations of the Grand River Wastewater Lagoons Forcemain Upgrade Construction$697.1K
- Upgrade of a Communal Waste Water Lagoon System, Ohsweken, Ontario$500.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51497 in the federal list. How to read these figures.