Seasonal wastewater lagoon optimization

Constance Lake First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$49,672
Federal share50%

of $99.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020202120222023
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Constance Lake First Nation
Construction start
May 1, 2018(actual)
Construction end
Aug 31, 2023(actual)

Against the original forecast

  • Construction start8 months lateforecast Sep 1, 2017
  • Construction end5 months lateforecast Mar 31, 2023

Also in Constance Lake First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51499 in the federal list. How to read these figures.