Seasonal wastewater lagoon optimization
Constance Lake First Nation, Ontario
Federal contribution
$49,672
Federal share50%
of $99.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020202120222023
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Constance Lake First Nation
- Construction start
- May 1, 2018(actual)
- Construction end
- Aug 31, 2023(actual)
Against the original forecast
- Construction start8 months lateforecast Sep 1, 2017
- Construction end5 months lateforecast Mar 31, 2023
Also in Constance Lake First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51499 in the federal list. How to read these figures.