Decommissioning of 13 wells

Alderville First Nation, Ontario

underwayDrinking WaterCWWF
Federal contribution
$13,282
Federal share50%

of $26.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020202120222023
BuiltForecast

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Alderville First Nation
Construction start
Jan 1, 2019(actual)
Construction end
Sep 22, 2023(forecast)

Against the original forecast

  • Construction start20 months lateforecast May 1, 2017