Class 4 Septic System Replacements (Tank and Field) for 8 Homes

Big Grassy First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$61,011
Federal share48%

of $128.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Big Grassy First Nation
Construction start
Nov 30, 2017(actual)
Construction end
Aug 30, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast Jun 5, 2017
  • Construction end12 months lateforecast Aug 31, 2017