Class 4 Septic System Replacements (Tank and Field) for 8 Homes
Big Grassy First Nation, Ontario
Federal contribution
$61,011
Federal share48%
of $128.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
2018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Big Grassy First Nation
- Construction start
- Nov 30, 2017(actual)
- Construction end
- Aug 30, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast Jun 5, 2017
- Construction end12 months lateforecast Aug 31, 2017
Also in Big Grassy First Nation